Two projects in Paola will add ten apartments to Malta’s social housing stock, Housing Minister Owen Bonnici said during a site visit.

Developed by Housing Projects Solutions, each project will provide five apartments for allocation by the Housing Authority.

The Triq ix-Xewk development, on the corner with Triq Carmelo Robinich, will comprise five one-bedroom units. The €440,000 project is expected to finish by mid-July 2027.

At Triq Imbroll, construction has reached the third floor, with civil works expected to finish by the end of January 2027 before subsequent phases. Civil works cost €260,000, with finishing and mechanical and electrical installations estimated at €203,000.

Source and photo: Department of Information, PR262034.